KOCHI SSI : LETTER TO ALL ALLOTTEES:-REVISED DESIGN OF TOILET DOOR; BELGAUM KUDCHI PH-II : LETTER TO ALL REGISTRANTS; BELGAUM JJAY (PH-II) : OPENING OF SPOT SCHEME FROM 24 JUN 2015 TO 21 SEP 2015; COIMBATORE : LETTER TO ALLOTTEES; KOLKATA (PH-II) : REVISION OF PAYMENT SCHEDULE; DEHRADUN (REGULAR) : SURPLUS PARKING AVAILABLE; BANGALORE WHITEFIELD : REVISED SCHEDULE FOR BLOCK C (TOWER 11 & 12); PANCHKULA SEC-27 : OPEN HOUSE FOR ALLOTTEES; NEWSLETTER (APR 2015); NASHIK PH-II : REVISION OF PAYMENT SCHEDULE; MOHALI SEC-114 : REGISTRATION OPEN FOR CIVILIANS ; LUCKNOW (VRINDAVAN AWAS YOJANA) : AFFIDAVIT LV6 & LV8; SECUNDERABAD JJAY : COSTING; CHENNAI (OMR) PH-II : OPENING OF DEMAND SURVEY FROM 15 MAR TO 15 JUN 15; CHENNAI OMR : REVISION OF PAYMENT SCHEDULE; LUCKNOW (VRINDAVAN AWAS YOJANA) : NOC FROM LDA; LUCKNOW (VAY) : CONVERSION OF DEMAND SURVEY REGISTRATION TO ANNUAL REGISTRATION; KOCHI SSI : REVISION OF PAYMENT SCHEDULE; BAHADURGARH (JJAY) : LEVY OF ENHANCED COMPENSATION BY GOVT OF HARYANA; GURGAON SEC-95 : REVISION OF PAYMENT SCHEDULE; COIMBATORE : REVISION OF PAYMENT SCHEDULE;
 
Chennai (OMR Turnkey)
 
.
 

Latest Update (as on 07-07-15)



UTILISATION OF COMMON FACILITIES: OMR, CHENNAI PHASE I & II


It is intimated that the common facilities of Club House (executed in the ongoing Phase-I) and Shopping Complex (planned in Phase-II) are for use by allottees of both phases I and II.

Present progress is 48.81% as on 30 Jun 2015.

LETTER TO ALL ALLOTTEES FOR PROPOSED VALUE ADDITIONS

REVISION OF PAYMENT SCHEDULE
OMR CHENNAI PROJECT

* Please refer to Para 40 of AWHO Master Brochure Jul 87 (as amended)
* Due to unavoidable reasons the physical progress of the project is yet to match the planned progress.  All efforts are being made to speed and complete the work by PDC already announced.
* In order to adhere to construction linked payment schedule, it has been decided to re-schedule the payment schedule of OMR Chennai Project as under :-

For Allottees with payment schedule As Under.
First instalment - 25% cost of DU,
Second to Fifth instalment - 15% cost of DU
Sixth instalment - 10% cost of DU

Ser

No

Type of Payment

Instalment No

Existing Due Date

Revised Date of Payment

(i)

15% of Construction cost

5th

15 Apr 2015

09 Oct 2015

(ii)

10% of Construction cost

6th

03 Nov 2015

 19 Feb 2016



For Allottees with Payment Schedule As Under.
First Instalment - 35% cost of DU
Second Instalment - 20% cost of DU
3rd and 4th Instalment - 15% cost of DU
5th Instalment - 10% cost of DU

Ser

No

Type of Payment

Instalment No

Existing Due Date

Revised Date of Payment

(i)

15% of Construction cost

4th

15 Apr 2015
27 May 2015
01 Jul 2015
05 Aug 2015
23 Sep 2015


09 Oct 2015

(ii)

10% of Construction cost

5th

03 Nov 2015
20 Jan 2016

19 Feb 2016


* The above revised payment schedule be adhered to.
* There is no change in the amount of instalment and other terms & conditions as given in the booking letter.

 

AWHO PROJECT OMR CHENNAI

AWHO Project at OMR Chennai has now picked up pace and the structural work is progressing at good speed. Out of six towers each with two stilts and 29 floors, one tower of 2BHK and one tower of 3BHK have been completed. At present pace, two more towers will be completed by June 2015 and balance two towers will be completed by Dec 2015. Finishing work has commenced in two towers and sample flats of all categories have been completed.

Club house structure is at third floor level out of a total of five floors.

In the Non tower areas, stilt I and II level slabs have been laid and podium slab is under construction.

Issues of provision of piped water supply of metro water and construction of approach road from DLF garden city to the project are being pursued with the TN State Government, and are being closely monitored.

Value Additions being provided
* Double stilt parking instead of basement + stilt planned earlier
* Compound wall on pile foundation.
* Additional common areas in stilt I & II
* 2 BHK 141 Sq m
* 3 BHK 47 Sq m
* 4 BHK 81 Sq m
* Granite flooring in corridors and staircase in lieu of green marble

As a value addition piped LPG supply to all residential units is being planned.
Case for exemption of stamp duty (6%) and registration charges (1%) has been taken up with TN State Government.



ELEVATED ROAD TO CONNECT TARAMANI AND MAMALLAPURAM

HOMES IN SUBURBS TURN COSTLIER AS CITY GROWS

RENTALS IN CITY GO THROUGH THE ROOF


 
 
Project Progress...
.
 
 
 
 
Copyright 2010 AWHO All rights reserved.

Browser compatibility IE 7.0 onwards, Mozilla 3.6,
Google Chrome, Safari. Best viewed in 1024 x 768 .