GREATER NOIDA PH-IV : OPTION LETTER FOR ALLOTMENT OF SPECIFIC DUs; BANGALORE (WHITEFIELD):REVISED H/T SCHEDULE; DEHRADUN REGULAR : SURPLUS PARKING; DEHRADUN (REG & JJAY) : HANDING/TAKING OVER INSTRUCTIONS; PUNE (HADAPSAR) PHASE-II : DRAW RESULT OF PARKINGS; COIMBATORE : REVISION OF PAYMENT SCHEDULE; PUNE WAGHOLI : DELAY IN COMMENCEMENT OF CONSTRUCTION WORK; DEHRADUN (REG & JJAY) : HANDING/TAKING OVER SCHEDULE ; BANGALORE WHITEFIELD : DRAW RESULT OF SUPPLEMENTARY PARKING ; MEERUT (RAKSHAPURAM) : DEMAND SURVEY ; BELGAUM JJAY : HANDING TAKING OVER INSTRUCTIONS ; OMR CHENNAI (TURNKEY) : REVISION OF PAYMENT SCHEDULE; KANDAGHAT, HP : EXPRESSION OF INTEREST; PANCHKULA SEC-27 : REVISED H/T SCHEDULE; BANGALORE (WHITEFIELD) : H/T SCHEDULE; VADODARA : EXPRESSION OF INTEREST;
 
Chennai (OMR Turnkey)
 
.
 

Latest Update (as on 27-08-14)


Present progress is 29% as on 31 Jul 2014.
 

REVISION OF PAYMENT SCHEDULE
OMR CHENNAI PROJECT

* Due to unavoidable reasons the physical progress of the project is yet to match the planned progress.  All efforts are being made to speed and complete the work by PDC already announced.
* In order to adhere to construction linked payment schedule, it has been decided to re-schedule the payment schedule of OMR Chennai Project as under :-

For Allottees with payment schedule As Under.
First instalment - 25% cost of DU,
Second to Fifth instalment - 15% cost of DU
Sixth instalment - 10% cost of DU

Ser

No

Type of Payment

Instalment No

Existing Due Date

Revised Date of Payment

(a)

15% of Construction cost

4th

20 Jun 2014

19 Sep 2014

(b)

15% of Construction cost

5th

15 Dec 2014

15 Apr 2015

(c)

10% of Construction cost

6th

03 Apr 2015

03 Nov 2015



For Allottees with Payment Schedule As Under.
First Instalment - 35% cost of DU
Second Instalment - 20% cost of DU
3rd and 4th Instalment - 15% cost of DU
5th Instalment - 10% cost of DU

Ser

No

Type of Payment

Instalment No

Existing Due Date

Revised Date of Payment

(a)

15% of Construction cost

3rd

20 Jun 2014
26 Jun 2014
24 Jul 2014
27 Aug 2014

19 Sep 2014

25 Sep 2014
29 Oct 2014
27 Nov 2014

No change

(b)

15% of Construction cost

4th

15 Dec 2014
15 Jan 2015

15 Apr 2015

(c)

10% of Construction cost

5th

03 Apr 2015

03 Nov 2015


* The above revised payment schedule be adhered to.
* There is no change in the amount of instalment and other terms & conditions as given in the booking letter.


ELEVATED ROAD TO CONNECT TARAMANI AND MAMALLAPURAM

HOMES IN SUBURBS TURN COSTLIER AS CITY GROWS

RENTALS IN CITY GO THROUGH THE ROOF


 
 
Project Progress...
.
 
 
 
 
Copyright 2010 AWHO All rights reserved.

Browser compatibility IE 7.0 onwards, Mozilla 3.6,
Google Chrome, Safari. Best viewed in 1024 x 768 .