Update : As on 15-05-2025
POST EC COMPLIANCE REPORT : AWHO PROJECT, VIJAY VIHAR, WAGHOLI, PUNE
ENVIRONMENTAL CLEARANCE LETTER DATED 23.12.2013
ENVIRONMENTAL CLEARANCE LETTER DATED 12.03.2018
LATEST ENVIRONMENTAL STATEMENT (FORM V)
Update : As on 22-01-2025
|
EXECUTING OF CONVEYANCE DEED / REGISTRATION OF ALLOTTED DWELLING UNIT AT GURGAON 95, PUNE WAGHOLI AND MOHALI–114 PROJECTS |
Update : As on 14-06-2022
CRITICAL OBSERVATIONS ON WATER SUPPLY TO DUs AT VIJAY VIHAR PROJECT, PUNE (WAGHOLI)
Update : As on 16-02-2022
|
RECEIPT OF OC FOR TOWERS D, E, G, H, J & K AWHO WAGHOLI, PUNE PROJECT 1. Allottees are informed that Occupation Certificate (OC) for Vijay Vihar Wagholi, Pune project in respect of Towers D, E, G, H, J & K dated 15 Feb 2022 has been received from Pune Metropolitan Region Development Authority (PMRDA), Pune. Same is enclosed. OC in respect of Towers A, B, C, F, L & M had already been received earlier and intimated to allottees vide web update dated 18 Nov 2020.
|
Update : As on 01-02-2022
|
FACILITY MAINTENANCE SERVICES AWHO VIJAY VIHAR, WAGHOLI (PUNE) PROJECT 1. Reference our web update dated 09 Feb 2021. |
Update : As on 02-12-2021
Update : As on 25-11-2021
|
ELECTION OF RWA AT AWHO VIJAY VIHAR, PUNE (WAGHOLI) 1. The Elections for RWA, AWHO Vijay Vihar were conducted as per guidelines issued by HQ AWHO vide letter No B/03001/55/AWHO/Pune/Wagholi dated 10 Nov 2021. |
Update : As on 11-11-2021
ELECTION FOR RWA AT AWHO VIJAY VIHAR, PUNE(WAGHOLI)
Update : As on 22-10-2021
OPENS DEMAND SURVEY FOR AWHO HOUSING PROJECT AT PUNE WAGHOLI PHASE-II FROM 25 OCT 2021 TO 24 JAN 2022 (EXTENDED UPTO 31 MAR 2022)
Update : As on 06-10-2021
Update : As on 31-08-2021
CLARIFICATIONS ON THE ISSUES RAISED BY ALLOTTEES OF AWHO WAGHOLI, PUNE PROJ
Update : As on 05-07-2021
|
POSTPONEMENT OF COMMENCEMENT DATE OF HANDING OVER, LAST DATE OF PAYMENT AND DATE OF COMMENCEMENT OF CARETAKING CHARGES FOR TOWERS D, E, G, H, J & K : AWHO WAGHOLI, PUNE PROJECT 1. Further to web update on 27 May 2021.
3. This is for information of all concerned. |
Update : As on 31-05-2021
|
PUNE WAGHOLI : 1. Refer our web update dated 09 Feb 2021. |
Update : As on 27-05-2021
Update : As on 03-05-2021
|
PUNE (WAGHOLI) : LATEST UPDATE 1. Reference web update dated 15 Feb 2021 vide which amended schedule of H/T over of DUs was promulgated to allottees. |
Update : As on 01-04-2021
|
WAIVER OF RESTRICTION OF SALE PERIOD AFTER TAKING OVER THE POSSESSION BY ALLOTTEES OF PUNE (WAGHOLI) 1. Reference Para 80 to 84 of AWHO Master Brochure Jul 87 (as amended upto Jun 2019). |
Update : As on 15-02-2021
|
AWHO WAGHOLI, PUNE PROJECT 1. Reference web updates dated 16 Nov and 28 Dec 2020 vide which amended schedule of H/T over of DUs was promulgated to allottees. 2. Due to unforeseen delays in getting electric supply from Lonikand Power Stn of MSEDCL, it has been decided to revise the H/O schedule of D, E, G, H, J & K towers as under:-
3. Taking over of DUs conditionally on an undertaking shall remain open for all allottees subject to their clearing all dues & receipt of clearance letter from HQ AWHO, in order to avail discount on registration charges / stamp duty and carry out interior works in their DUs. However, allottees will be able to reside in the DU only after OC is received for the same. 4. AWHO shall be running the essential services like electric supply, water supply, lifts, etc for the allottees till sufficient occupancy is achieved and / or AUC / RWA is formed. |
Update : As on 09-02-2021
|
AWHO WAGHOLI, PUNE PROJECT : LATEST UPDATE 1. Reference our web update dated 16 Nov 2020 and visit of MD AWHO to the project on 17 Dec 2020. |
Update : As on 28-12-2020
|
AWHO WAGHOLI, PUNE PROJECT 1. Ref web update dated 16 Nov 2020 vide which amended schedule of H/T over of DUs was promulgated to allottees.
3. Rest of the provisions of web update dated 16 Nov 2020 shall remain unchanged. |
Update : As on 24-11-2020
Update : As on 18-11-2020
| RECEIPT OF PART OCCUAPTION CERTIFICATE (OC) VIJAY VIHAR, WAGHOLI (PUNE) 1. It is to intimated that Part Occupation Certificate (OC) for Vijay Vihar Wagholi, Pune project in respect of Towers A, B, C, F, L & M dated 09 Nov 2020 has been received from Pune Metropolitan Region Development Authority (PMRDA), Pune. Same is enclosed. 2. With receipt of Part OC, signing of undertaking by allottees of the above mentioned towers is being done away with. |
Update : As on 16-11-2020
|
1. Ref web update dated 17 Jul 20 vide which schedule of H/T over of DUs was promulgated to allottees; and web update dt 30 Sep 20 vide which allottees of towers A, B, C, F, L & M were given option to take over flats conditionally wef from 01 Oct 20.
|
Update : As on 26-10-2020
|
AWHO WAGHOLI (PUNE) 1. Refer our update dated 07 Jul 2020. |
Update : As on 30-09-2020
|
COMMENCEMENT OF HANDING OVER 1. Refer our update dated 17 Jul 2020 indicating the re-sch of commencement of handing over of DUs. |
Update : As on 25-09-2020
DRAFT CONVEYANCE DEED FOR REGN OF DUS AT VIJAY VIHAR, WAGHOLI, PUNE (AWHO PROJECT)
Update : As on 22-07-2020
CLARIFICATION ON CERTAIN ISSUES RAISED AWHO WAGHOLI, PUNE PROJECT
Update : As on 17-07-2020
|
RE –SCHEDULE OF COMMENCEMENT OF HANDING OVER 1. Further to AWHO ‘Update’ on 07 Jul 2020 indicating the commencement of handing over of DUs of 03 Towers wef 30 Sep 2020. The project will be handed over in group of three towers each. Accordingly, a schedule of handing/ taking over of various towers in the project is as under :-
2. These timelines are however subject to easing of lockdown imposed due to COVID -19. |
Update : As on 07-07-2020
|
RE-SCHEDULE OF LAST DATE OF PAYMENT IN R/O AWHO PROJECT WAGHOLI (PUNE) Further to our update dated 08 Jun 2020 with respect to commencement of handing over of DUs. Due to continuation of lockdown in Maharashtra and shortage of labour on site due to COVID-19, the commencement of handing over of DUs at Wagholi, Pune in r/o Towers A, F & M is postponed till 30 Sep 2020 with the last date of payment as 15 Oct 2020. All out efforts will be made to commence handing over prior to 30 Sep 2020 and allottees will be intimated in advance should the situation improve. Allottees wanting to take over their DU shall have to make full payment and obtain clearance from AWHO prior to taking over. The handing over schedule shall be further reviewed in the first week of Sep 2020, based on situation prevailing at that time. |
Update : As on 08-06-2020
|
RE-SCHEDULE OF LAST DATE OF PAYMENT IN R/O AWHO PROJECT WAGHOLI (PUNE) Further to our update dated 07 Apr 2020 and extension of countrywide lockdown by Govt of India. Fresh dates to commence handing over of DUs of tower ‘A’, ‘F’ &’M’ of AWHO Project Wagholi (Pune) has been postponed to 15 Jul 2020 and last date of payment has been postponed to 31 Jul 2020. Handing/taking for tower ‘A’, ‘F’ and ‘M’ will commence for the allottees who would have paid final dues till 14 Jul 2020. This shall be further reviewed in first week of Jul 2020 based on situation prevailing at that time. |
Update : As on 07-04-2020
|
RE-SCHEDULE OF LAST DATE OF PAYMENT IN R/O AWHO PROJECT WAGHOLI (PUNE) Due to COVID-19 outbreak and subsequent nationwide lockdown, the last date of payment for allottees of Tower ‘A’, ‘F’ &’M’ of AWHO Project Wagholi (Pune) has been postponed to 30 Jun 2020. Handing/taking for tower ‘A’, ‘F’ and ‘M’ will commence wef 15 Jun 2020 for the allottees who would have final dues till 14 Jun 2020. This shall be further reviewed in last week of May 2020 based on situation prevailing at that time. |
Update : As on 25-03-2020
Due to the COVID-19 outbreak and subsequent nationwide lock down the last date of payment for Pune Wagholi has been postponed as under :-
| S.NO. | LAST DATE OF PAYMENT | POSTPONED TO |
| 1 | 25 Mar 2020 & 10 Apr 2020 |
25 APR 2020 |
Update : as on 24-03-2020
RELAXATION IN PROPERTY TAX FOR EX-SERVICEMEN & WAR WIDOWS
Maharashtra govt has given relaxation in property tax to ex-servicemen and war widows. An extract of the news item is as encl. However, registrants should have a domicile of Maharashtra.
Update : as on 23-03-2020
|
HANDING/TAKING OVER SCHEDULE Handing/Taking Over Schedule of AWHO Wagholi is presently postponed by a month due to the effect of COVID-19 Virus, leading to delay in obtaining Occupation Certificate (OC), due to restricted functioning of the State Government. The fresh schedule shall be communicated subsequently, depending on the ground situation. |
Update : as on 18-03-2020
|
PROVISION OF METRO STN Consequent to request and liaison by AWHO and HQ Southern Command, Maharashtra Metro Rail Corporation Ltd (MMRCL) vide their letter dt 27 Feb 2020 have agreed to consider planning a Metro Stn close to AWHO Wagholi project during the preparation of DPR for Ramwadi – Wagholi stretch. This is for info of all allottees. |
Update : as on 20-01-2020
HANDING TAKING OVER INSTRUCTIONS
Update : Progress as on 31-12-19
Project Progress (Including Land Cost) : 97.27%
Constr Progress : 96.00%
Update : as on 17-12-19
|
WAGHOLI, PUNE : H/O OF DUs Commencement of DUs handing over planned from Apr 2020 onwards. The Final Statement of Account (FSA) shall be sent towerwise approx 02 months in advance of the handing over date. The current progress of project is 95%. |
Update : Progress as on 30-11-19
Project Progress (Including Land Cost) : 96.07%
Constr Progress : 94.25%
Update : Progress as on 31-10-19
Project Progress (Including Land Cost) : 95.22%
Constr Progress : 93.00%
Update : as on 29-10-19
DU NUMBERING PLAN : WAGHOLI (PUNE) PH-I PROJECT
Update : as on 25-10-19
|
PUNE WAGHOLI : NOTICE FOR ALLOTTEES 1. It has been observed that after conduct of draw of lots for allotment of DUs and Car Parking, allottees are quite eager to see their individual DUs and have started visiting at site. |
Update : as on 15-10-19
Draw result for Pune (Wagholi) Project for DUs & Parking held on 11 Oct 2019 has been uploaded on the website.
Update : Progress as on 30-09-19
Project Progress (Including Land Cost) : 94.67%
Constr Progress : 92.20%
Update : Extention of Option Date
1. Reference option letter for specific floor & parking spaces of Pune (Wagholi) Project.
2. The last date of receipt of option has been extended from 13 Sep 2019 to 30 Sep 2019.
3. Allottees are requested to submit their options duly filled with AWHO by due date to enable AWHO to hold the draw smoothly.
Update : Progress as on 31-08-19
Project Progress (Including Land Cost) : 93.85%
Constr Progress : 91.00%
Update : as on 26-08-19
OPTION LETTER FOR SPECIFIC FLOOR AND PARKING SPACE
Update : Progress as on 31-07-19
Project Progress (Including Land Cost) : 93.24%
Constr Progress : 90.10%
Update : as on 30-07-19
OPENS DEMAND SURVEY FROM 01 AUG 2019 TO 29 SEP 2019
Update : as on 17-07-19
PUNE (WAGHOLI) : PAYMENT OF LAST INSTALLMENT
Update : as on 09-07-19
|
ADDITIONAL EXPENDITURE FOR PROVISION OF ELECTRIC SUPPLY 1. AWHO Wagholi Project was planned with a commitment from ‘Maharashtra State Electricity Distribution Company Limited (MSEDCL)’ to provide full power requirement of the project. Accordingly while computing the initial DU cost, the expenditure on this account catered to only the electrical infrastructure within the project, with the assumption that MSEDCL would provide the power at the periphery of the project. |
Update : Progress as on 30-06-19
Project Progress (Including Land Cost) : 92.83%
Constr Progress : 89.50%
Update : as on 17-06-19
Update : Progress as on 31-05-19
Project Progress (Including Land Cost) : 91.98%
Constr Progress : 88.25%
Update : Progress as on 30-04-19
Project Progress (Including Land Cost) : 90.27%
Constr Progress : 85.75%
Update : Progress as on 31-03-19
Project Progress (Including Land Cost) : 89.76%
Constr Progress : 85.00%
Update : as on 19-03-19
Lt Gen S K Saini, AVSM,YSM,VSM, GOC-in-C, HQ Southern Command visited the AWHO Wagholi, Project site on 07 Mar 2019. The Gen Offr conveyed his appreciation for the good work being done. Few Photographs of the visit are attached.
| Times of India, Pune newspaper cutting dated 09 Mar 2019 in respect of Bhama Askhed Water Supply line is att herewith.This pipe line is catering for water supply to Eastern part of Pune under PMC. This pipe line would be passing through Lohegaon, further to Viman Nagar and Kalyani Nagar. PMRDA would in all likelihood demand water for Wagholi from this pipe line. However, at present there is no assurance from the PMC. Further progress on this issue shall be monitored and intimated |
Update : Progress as on 28-02-19
Project Progress (Including Land Cost) : 88.90%
Constr Progress : 83.75%
Update : Progress as on 31-01-19
Project Progress (Including Land Cost) : 88.05%
Constr Progress : 82.50%
Update : Progress as on 31-12-18
Project Progress (Including Land Cost) : 87.20%
Constr Progress : 81.25%
Update : Progress as on 30-11-18
Project Progress (Including Land Cost) : 85.32%
Constr Progress : 78.50%
Update : Progress as on 31-10-18
Project Progress (Including Land Cost) : 84.40%
Constr Progress : 77.15%
Latest Update : As on 25-10-18
|
Update of Individual Running Ledger Account (IRLA) (a) Immediately after transferring amount through bank, allottees are required to intimate Registration No, UTR/NEFT No with Date of Transaction and amount details by e-mail to AWHO. |
|
AD FOR DWELLING UNITS AT PUNE WAGHOLI PROJECT 1. Avail last opportunity to own a Dwelling unit from AWHO at Pune Wagholi. Few dwelling units are available for allotment on first come first serve basis. The details of available dwelling units are as under :-
2. Prices of dwelling units are likely to be revised wef 01 Jan 2019 onwards. |
Update : Progress as on 30-09-18
Project Progress (Including Land Cost) : 83.69%
Constr Progress : 76.11%
Update : Vijay Vihar (as on 19-09-18)
Progress of work is 74.11% as on 31 Aug 2018.
Update : Vijay Vihar (as on 02-08-18)
Progress of work is 73.5% as on 31 Jul 2018.
Update : Vijay Vihar (as on 04-07-18)
Progress of work is 72.2% as on 30 Jun 2018.
Update : Vijay Vihar (as on 07-06-18)
Progress of work is 70% as on 31 May 2018.
Update : Vijay Vihar (as on 04-06-18)
EXTENSION OF DUE DATE OF 5th INSTALMENT OF PUNE WAGHOLI PROJECT FROM 31 MAY 2018 TO 08 JUN 2018 DUE TO NATION WIDE BANK STRIKE ON 30 & 31 MAY 2018.
Update : Vijay Vihar (as on 05-05-18)
Progress of work is 68% as on 30 Apr 2018.
Update : Vijay Vihar (as on 18-04-18)
Update : Vijay Vihar (as on 06-04-18)
Progress of work is 65.7% as on 31 Mar 2018.
Update : Vijay Vihar (as on 05-04-18)
Update : Vijay Vihar (as on 13-03-18)
PRE-PONEMENT OF 4TH INSTALMENT : PUNE WAGHOLI PROJECT
Update : Vijay Vihar (as on 12-03-18)
Progress of work is 64% as on 28 Feb 2018.
Update : Vijay Vihar (as on 06-02-18)
Progress of work is 62% as on 31 Jan 2018.
Update : Vijay Vihar (as on 12-01-18)
|
CHOICE OF SPECIFICATIONS 1. Please refer ‘Choice of Specifications’ clause given at Page No. 2 of Technical Brochure. |
Update : Vijay Vihar (as on 10-01-18)
Progress of work is 60.3% as on 31 Dec 2017.
Update : Vijay Vihar (as on 06-12-17)
Progress of work is 58.5% as on 30 Nov 2017.
Update : Vijay Vihar (as on 20-11-17)
Progress of work is 57.5% as on 31 Oct 2017.
Update : Vijay Vihar (as on 04-10-17)
Progress of work is 53.7% as on 30 Sep 2017.
Update : Vijay Vihar (as on 29-09-17)
OPENING OF AWHO PUNE WAGHOLI (PWG) PROJECT FOR CIVILIANS
Update : Vijay Vihar (as on 05-09-17)
Progress of work is 50.5% as on 31 Aug 2017.
Update : Vijay Vihar (as on 04-09-17)
The Times of India article published on 12 Aug 2017 : SHOULD YOU INVEST IN WAGHOLI?
Update : Vijay Vihar (as on 30-08-17)
Regn Certificate and Escrow/Separate Project Account under MAHARASHTRA RERA
Update : Vijay Vihar (as on 03-08-17)
Progress of work is 48% as on 31 Jul 2017.
Update : Vijay Vihar (as on 25-07-17)
The visualization of the Walk Through is depictive in nature. However, for actual specifications please refer Technical Brochure of the project.
Update : Vijay Vihar (as on 11-07-17)
Progress of work is 45% as on 04 Jul 2017.
Update : Vijay Vihar (as on 06-07-17)
|
PRE-PONEMENT OF 3rd INSTALMENT 1. We are glad to inform you that the progress of construction of Pune Wagholi Project is well ahead of the schedule in comparison to the schedule envisaged by us.
4. Inconvenience caused is deeply regretted. |
Update : Vijay Vihar (as on 29-06-17)
|
LATEST UPDATE (a) Ref choice of specification clause mentioned at page 2 of TB. SAMPLE PHOTOGRAPHS :- * SUPER DELUXE |
Update : Vijay Vihar (as on 16-06-17)
Update : Vijay Vihar (as on 13-06-17)
Progress of work is 44% as on 10 Jun 2017.
Update : Vijay Vihar (as on 17-05-17)
Progress of work is 38.5% as on 30 Apr 2017.
Update : Vijay Vihar (as on 12-04-17)
ALLOTMENT OF ADDITIONAL DWELLING UNIT (DU) TO THE EXISTING ALLOTTEES IN THE SAME STATION/ PROJECT
Update : Vijay Vihar (as on 10-04-17)
Progress of work is 35.5% as on 31 Mar 2017.
Latest Update : Vijay Vihar (as on 02-03-17)
Progress of work is 32% as on 28 Feb 2017.
Update : Vijay Vihar (as on 20-02-17)
Progress of work is 30.6% as on 15 Feb 2017.
Update : Vijay Vihar (as on 08-02-17)
Progress of work is 26.8% as on 31 Jan 2017.
Update : Vijay Vihar (as on 03-01-17)
Present progress of work is 25% as on 30 Dec 2016.
Update : Vijay Vihar (as on 30-11-16)
Present progress of work is 22% as on 30 Nov 2016.
Update : Vijay Vihar (as on 16-11-16)
Keeping in view the present bank scenario, due to demonetization of currency and numerous requests received from allottees, the due date for installment due on 15Nov 2016 has been extended to 30Nov 2016. Rest NO change.
Present progress of work is 19% as on 03 Nov 2016.
Update : Vijay Vihar (as on 04-10-16)
Present progress of work is 15% as on 30 Sep 2016.
OPENING OF REGISTRATION FOR AIR FORCE AND NAVAL PERSONNEL
OPENING OF REGISTRATION FOR ASSAM RIFLES AND GREF PERSONNEL
PUNE WAGHOLI : WALKTHROUGH VIDEO
WONDERFUL WAGHOLI : PROMISING RESIDENTIAL AND COMMERCIAL DESTINATION
OPENING OF REGISTRATION FOR PRIORITY-II APPLICANTS : PUNE WAGHOLI (PWG) PROJECT
Update : Vijay Vihar (as on 15-09-16)
Present progress of work is 12.25% as on 31 Aug 2016.
Update : Vijay Vihar (as on 15-07-16)
Present progress of work is 9.5% as on 31 Jul 2016.
|
AMENDMENT IN TECHNICAL BROCHURE * The following amendments may please be made in column No (d) i.e. Wall Area against Ser No 2 i.e. Super Deluxe Apts (SDA) at Page No 4 of our Technical Brochure :- |
|
Pune Wagholi : Updates
1. The earlier option of arranging water by “Wagheshwar Badhkam Vyavsik Association” from Bhima River or a dedicated water pipeline from Wadhu (Kd) to AWHO project has not fructified.2. It has been seen that a number of societies in the vicinity are functioning on ground/tanker based water supply. However, a pipeline from Bhama Ashked is being laid by the State Govt which may cover Wagholi also in the near future, the details of which is not known as of now. 3. The AWHO project Wagholi is therefore being launched on ground/tanker based water supply. 4. The Project will be executed in two Phases, Phase I constr details are:- (a) Total of 728 DU’s to be constructed as under:-
(b) Central facilities planned to be constructed in Phase- I are:- (i) Community Hall. (ii) Shopping Centre. (iii) STP. (c) Swimming pool has been planned in Phase-II. (d) Details of Phase-II will be intimated later. 5. Approval of building plans with enhanced FSI is in process. |
Offer Letter for DU at PUNE WAGHOLI for Waitlisted Registrant of PUNE(HADAPSAR PH-II)
Rising popularity of Pune( Wagholi)
| Environmental clearance for AWHO project at Pune (Wagholi) has been granted by the Govt of Maharashtra Environment Dept in the last week of Dec 2013. |